Post-hole concrete Calculator

Calculate concrete around round fence or other posts in round holes.

Back to the toolbox

How to use this calculator

01

Your measurements

Choose the unit beside each measurement. Changing a unit converts your value.

mm
mm
m
%

View your estimate

The post is assumed to extend through the full filled depth. Square posts require a different volume deduction. Hole dimensions must come from your project specification.

YOUR ESTIMATE

Concrete required

0.332m³
Net concrete volume0.302 m³
Concrete per hole0.038 m³

Same quantity, different units

Concrete required

m³
0.3318
yd³
0.4339
ft³
11.7157

Calculated from your measurements.

Pricing calculator

Use your supplier’s rate or enter a quoted total. Save each estimate to your project and print everything together.

Your selected quantity already includes any allowance shown in that result. Check whether you are pricing individual items or whole packs. Delivery, tax and labour are not added automatically. A quoted total applies only to this saved calculation.

Post-hole concrete Calculator: measuring notes and method

Measure hole and post separately

Measure the concrete-filled depth, which may be less than the excavated depth. Use Quantity only for holes with matching hole diameter, round post diameter and filled depth. Save gate posts and other differently sized holes as separate project items.

If the post stops above the hole bottom

Calculate the annular part around the post here, then add a separate solid cylinder for concrete below it. For a square post, subtract side × side × embedded depth from the round-hole volume separately.

Formula

Concrete = π × (hole diameter² − post diameter²) ÷ 4 × depth × quantity. Apply waste.

Product reference: QUIKRETE product yields

Worked examples in metric and imperial units

Illustrative values match Reset example and stay fixed when you edit the calculator. Both columns describe the same calculation; converted inputs are rounded.

Metric worked example

Hole diameter
300 mm
Round post diameter
100 mm
Filled depth
0.6 m
Quantity
8
Waste allowance
10 %

Concrete required: 0.3318 m³

Imperial worked example

Hole diameter
11.811 in
Round post diameter
3.937 in
Filled depth
1.9685 ft
Quantity
8
Waste allowance
10 %

Concrete required: 0.4339 yd³

Follow the calculation

Lengths in this working are in metres.

  1. Hole area minus round post area = π × (0.3² − 0.1²) ÷ 4 = 0.062832 m².
  2. Multiply that area by 0.6 m filled depth, 8 holes and the 1.1 allowance multiplier.

Unit conversions

1 m³ = 1,000 L ≈ 1.30795 yd³. One cubic yard is 27 ft³.

Reviewed 19 October 2026. How calculations are checked · Report a correction